Question 66

Which of the following conditions should the project manager consider when working on the scheduling for an adaptive environment?

  1. Defining, sequencing, estimating activity durations, and developing a schedule model are so tightly linked that they are viewed as a single process.
  2. The detailed project schedule should remain flexible throughout the project to accommodate newly gained knowledge.
  3. An iterative scheduling and on-demand, pull-based scheduling will be required.
  4. To address the full delivery schedule, a range of techniques may be needed and then need to be adapted.

Question 67

Which task will a project manager undertake while conducting Project Resource Management?

  1. Identify the different aspects of the team to manage and control physical resources efficiently
  2. Procure equipment, materials, facilities, and infrastructure for the project
  3. Train the team members in project skill sets
  4. Define the roles and responsibilities of each team member

Question 68

Which is an example of an internal enterprise environmental factor?

  1. Market share brand recognition
  2. Factory location
  3. Local government regulation
  4. Industry research

Question 69

Match each process with its corresponding description. Select and Place:

Question 70

A company must implement sales software because it is opening a new branch in a foreign market. Although this software is used in every domestic branch, multiple changes are expected during the implementation because it is a foreign location. Which type of life cycle would the project manager use in this case?

  1. Predictive life cycle
  2. Waterfall life cycle
  3. Hybrid life cycle
  4. Product life cycle