Question 11

Placement of a buried OSP pathway in public Rights of Way may require a permit based on which of the following?

  1. Locating of other utilities
  2. Bonding and grounding of metallic conductors
  3. Fees calculated on distance
  4. Building entrance conduit plugging

Question 12

What is the FIRST step in quality evolution (focused on physical quality) when developing a quality plan?

  1. Qualitative risk analysis
  2. Client satisfaction
  3. Conformance
  4. Client value
  5. Quantitative risk analysis

Question 13

Identify the fibers below as either single mode (SM) or multi mode (MM) by dragging the appropriate term into each oval.

Question 14

What’s the RECOMMENDED twisted pair cable slack length to be left at the work area outlet location to enable the possibility of future changes in the Horizontal Cabling System?

  1. ≈ 0.152 m (0.5 ft)
  2. ≈ 0.3 m (1 ft)
  3. ≈ 1 m (3 ft)
  4. ≈ 5 m (16.40 ft)

Question 15

During bidding the ICT distribution designer should review the bid responses for compliance and completeness. Afterwards, the designer should report the findings and recommendations to the _______

  1. technical consultant.
  2. legal counsel.
  3. stakeholders.
  4. construction foreman.