Question 6
True or False: The primary effect of limiting Work in Progress (WIP) is that it creates a pull system.
- True
- False
Question 7
What is the best chart to determine when a single item that has not been started will be finished?
- WIP Aging chart.
- Throughput run chart.
- Cycle Time scatterplot.
- Cumulative Flow diagram (CFD).
Question 8
Which of these is NOT a good description of Cycle Time?
- The length of time a work item stays in one column.
- The time a work item takes from initial idea/concept to feedback returned from customers after a production release.
- The time a work item starts until when it finishes.
- The number of items that move into the delivery/end point per time period (e g., daily/weekly).
Question 9
Which of these are typically included in the Definition of Workflow policies? (Choose six.)
- The Increment.
- Work Item types.
- Service Level Expectations.
- Gantt chart.
- WIP limits.
- Visualization policies.
- Pull/prioritization policies.
- Definition of Done.
- Burndown chart.