Question 6

True or False: The primary effect of limiting Work in Progress (WIP) is that it creates a pull system.

  1. True
  2. False

Question 7

What is the best chart to determine when a single item that has not been started will be finished?

  1. WIP Aging chart.
  2. Throughput run chart.
  3. Cycle Time scatterplot.
  4. Cumulative Flow diagram (CFD).

Question 8

Which of these is NOT a good description of Cycle Time?

  1. The length of time a work item stays in one column.
  2. The time a work item takes from initial idea/concept to feedback returned from customers after a production release.
  3. The time a work item starts until when it finishes.
  4. The number of items that move into the delivery/end point per time period (e g., daily/weekly).

Question 9

Which of these are typically included in the Definition of Workflow policies? (Choose six.)

  1. The Increment.
  2. Work Item types.
  3. Service Level Expectations.
  4. Gantt chart.
  5. WIP limits.
  6. Visualization policies.
  7. Pull/prioritization policies.
  8. Definition of Done.
  9. Burndown chart.