Question 1

For a specific Sprint Backlog item that has been started, what is the best chart (analytic) to determine when it will be finished?

  1. Work Item Aging Chart.
  2. Throughput Run Chart.
  3. Control chart.
  4. Cumulative Flow diagram (CFD).

Question 2

What might a Scrum Team visualize with Kanban? (Choose three.)

  1. The Product Backlog.
  2. The Sprint Backlog.
  3. The Definition of Done.
  4. The Sprint Retrospective.

Question 3

Which of the following is NOT a flow metric?

  1. Cycle Time.
  2. Work in Progress (WIP).
  3. Throughput.
  4. Work item age.
  5. All of the above are flow metrics.

Question 4

As input for Daily Scrum, which metrics are likely to provide the most actionable data?

  1. Leading indicators.
  2. Lagging indicators.

Question 5

Within the same Kanban system, Work in Progress (WIP), is NOT a leading indicator for:

  1. Throughput.
  2. Cycle Time.
  3. Number of Product Backlog items finished in a Sprint.
  4. Story points delivered.