Question 6
PRINCE2-Practitioner Edition 6
PRINCE2-Practitioner Edition 6 practice questions, page 2 of 2, with answer review and explanations.
Question 7
While preparing the Configuration Management Strategy, the Project Manager considered the options for change control. He decided to recommend a change budget of ֲ£250k, but was undecided on the Change Authority to recommend. Which option is an appropriate Change Authority for the Outsourcing project?
- The selected service provider to approve and implement all changes.
- Senior User(s) and Project Assurance representatives, within the limits of the recommended change budget.
- The Director of Facilities and the Director of Information Technology to approve all changes.