The project is part of a program to develop more training courses that respond to new legislation. The project manager has requested that project support be made available from the program. As a result, the executive has confirmed that this will be carried out by the program office. Is this appropriate, and why?
- Yes, because the program office should provide support to projects, if requested.
- Yes, because the project support role is not optional and must be provided.
- No, because the project manager should take on project support responsibilities.
- No, because program and project team structures need to be separate.
Question 3
Which management product defines the detailed nature, purpose and function of a product?
- Plan
- Quality Register
- Project Product Description
- Product Description
Question 4
Who sets the tolerances for a work package?
- The project board
- The project manager
- The team manager
- Corporate or programme management
Question 5
Who is responsible for committing user resources to the project?
- Senior User
- Senior Supplier
- Executive