PMI-ACP Practice Test

PMI-ACP Practice Test practice questions, page 13 of 20, with answer review and explanations.

Question 61

A project team meets to estimate user stories for a sprint. While an important non-functional requirement must be delivered in the sprint, the estimate exceeds sprint capacity. What should the team do?

  1. Estimate only functional requirements that will impact product quality
  2. Add team resources
  3. Refer the issue tot eh product owner
  4. Break non-functional requirements into those that can be delivered in the given sprint

Question 62

A development team and product owner disagrees on a user story in the product backlog. What should the agile practitioner do?

  1. Have the development team follow the product owner's direction
  2. Openly challenge the product owner in the effort to poke holes in their approach
  3. Facilitate a conversation about the user story between the development team and the product owner
  4. Serve as a nonpartisan evaluator of each option, and provide direction to the development team and product owner

Question 63

During a planning session, four out of five team members vote to include eight story points in a particular story, while the fifth member votes for five story points. How should this be handled?

  1. The story should be assigned eight story points as per the majority vote
  2. The story should be added to the backlog and reassessed later
  3. The story should be assigned points after a discussion with the fifth team member to see if a consensus can be reached
  4. The decision for the number of story points should be made by the customer

Question 64

A project is starting and the type of work is complex and suitable for agile. In assessing the team members, it appears that co-location would be a challenge. What should the agile practitioner do?

  1. Select and implement collaboration tools to augment team interactions
  2. Provide each geographical area with their own product owner and divide the work between the teams
  3. Increase the number of requirements documents and ensure they are clearly communicated
  4. After several sprints, calculate velocity based on primary team location and use secondary team as reserve

Question 65

Team A is working on the second sprint of a product release. Team B, which is an interdependent team located on the same floor, requires exclusive and frequent information to complete its sprint goal. What should the agile team do?

  1. Create a central repository for information, and provide access to team B
  2. Use an information board that will be visible to all passing through the workspace
  3. Email all stakeholders with status updates
  4. Provide team B with the information on an ג€as neededג€ basis