Question 41
After a release, the project sponsor received an escalation from an executive about the extension of the downtime after the scheduled window. Which of the following should be added to the issue log?
Continuous integration
Rollback plan
Customer notification
Automated testing
Question 42
Due to multiple changes, the sign-off for the project scope baseline is delayed. The project sponsor has restricted the budget for this project. Which of the following should the project manager MOST likely do to move forward?
Communicate with the affected stakeholders.
Initiate a formal change request to modify the cost.
Adjust the scope to stay within the cost.
Set a new cost using a lightweight estimation method.
Question 43
As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?
Document the request in the change control log.
Communicate the change deployment.
Conduct an impact assessment.
Implement the change.
Question 44
An IT intern was assigned to set up workstations as part of a project. The IT intern was very careful to do the task well and initially referred to notes while performing the task. By the end of the two-week rotation, the IT intern no longer needed the notes and completed more set-ups in less time. Which of the following MOST likely represents the observed relationship in this scenario?
Question 45
An opportunity emerged in the middle of a project life cycle. Which of the following is the BEST action for the project manager to take?