Question 46

The high-level technical requirements for a new application state that the application should be suitable to support enterprise-level client-server solutions. Which of the following meets these requirements?

  1. Data warehouse
  2. SQL database
  3. Multitier architecture
  4. Content management system

Question 47

A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Choose two.)

  1. Review the detailed plan.
  2. Develop a preliminary scope.
  3. Develop a transition plan.
  4. Develop a project management plan.
  5. Review the resource pool.
  6. Review the project objectives.

Question 48

A program manager is reviewing the project portfolio and prioritizing each project based on the company’s strategic plan. Which of the following should be considered in this evaluation? (Choose two.)

  1. Company vision
  2. Global environment
  3. Brand value
  4. Mission statement
  5. Portfolio budget
  6. Local legislation

Question 49

Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?

  1. Gantt chart
  2. Maintenance window schedule
  3. Functional requirements
  4. Test results

Question 50

A visual that displays team progress was created for stand-up meetings. Which of the following BEST describes what is being represented on the visual?

  1. Decision board
  2. Whiteboard
  3. Task board
  4. Dashboard