Question 26
Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?
Project change management plan
Project management plan
Project transition plan
Project communication plan
Question 27
A project team was instructed to refurbish old desktops. The following provides the details of the issues observed: Which of the following issues should be addressed FIRST?
Replace missing peripherals because this process can be easy and less costly.
An old operating system issue has the most amount of occurrences.
Damage to the monitor has the highest percentage.
Address each issue as discovered to avoid rework.
Question 28
A project manager was not part of a contract negotiation. The project manager is concerned that stakeholders will expect the project to achieve deliverables requested in the RFP. Which of the following documents should the project manager produce FIRST to start communication about the boundaries of the project?
Milestone chart
Work breakdown structure
Project charter
Detailed scope statement
Question 29
In a functional organization, a project has been completed successfully. Which of the following actions would the project manager MOST likely perform?
Assemble a new project with existing resources.
Obtain the final report from release management.
Notify the functional manager that resources are released.
Allocate resources in a different project.
Question 30
A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?