Question 21

During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?

  1. Issue log
  2. Defect log
  3. Change log
  4. Task board

Question 22

A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?

  1. ESG
  2. PHI
  3. PII
  4. ROIL

Question 23

A project manager has been very diligent in maintaining the version control for the documentation of requirements. Which of the following tools is the project manager using?

  1. Multiauthoring software
  2. Word processor
  3. Real-time polling
  4. Conferencing platforms

Question 24

The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?

  1. External
  2. Internal
  3. Mandatory
  4. Discretionary

Question 25

A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?

  1. Issue log
  2. Gantt chart
  3. Milestone chart