PK0-005 Practice Test practice questions, page 5 of 25, with answer review and explanations.
Question 21
During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?
Issue log
Defect log
Change log
Task board
Question 22
A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?
ESG
PHI
PII
ROIL
Question 23
A project manager has been very diligent in maintaining the version control for the documentation of requirements. Which of the following tools is the project manager using?
Multiauthoring software
Word processor
Real-time polling
Conferencing platforms
Question 24
The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?
External
Internal
Mandatory
Discretionary
Question 25
A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?