Question 101
A risk response in a project in your program has actually caused new risks. What term is assigned to the new risks that a risk response has created?
Reactionary risks
Chain risks
Secondary risks
In flux risks
Question 102
You are the program manager for your organization. You have proposed a program that will cost $750,000 and will last for four years. Management is concerned with the cost of the program in relation to the return your program will bring. If the rate of return is six percent what is the minimum value your project should return in four years based on the investment of the program?
$750,000
$795,000
$750,001
$946,857
Question 103
You are the project manager for the JJY Project, which is similar to the HHG Project you managed last quarter. You would like to model the current project scope on the previous project to save time and effort. This is an example of what kind of scope definition?
Analogous estimating
Organizational process assets
Parametric scope definition
Template driven
Question 104
What quality control chart compares two or more variables over time to determine how closely the variables may be related to one another?
Run chart
Scatter diagram
Control chart
Pareto diagram
Question 105
All of the following are resources that need to be monitored and controlled except for which one?