Question 91
Your program creates a byproduct that you could sell to a client. The cost of the byproduct would offset the cost of the program by nearly $7,500 per month. This is an example of which positive risk response?
Sharing
Enhance
Exploiting
Accepting
Question 92
You are the program manager for your company and management wants you to identify how you'll make decisions in the program planning processes. What program management document should serve as the baseline for all future program decisions?
Program budget
Program management plan
Program scope statement
Program requirements
Question 93
What percentage of communication is nonverbal?
55 percent
50 percent
90 percent
45 percent
Question 94
You are the program manager of the JNH Program. Tom, a project manager in your program, has just completed his project and is ready to officially close his project. You agree that Tom's project is completed. What role do you play in Tom's project closure?
You must ensure that the project sponsor closes the project.
You must ensure that that the projects within the program have been closed at the project level.
You must close the project before operations closes the project.
You must ensure that the program management team closes the project for the project manager.
Question 95
Which one of the following is NOT a component of the risk monitoring and controlling process?