Question 81
Two project managers in your program, Marcy and Mary, are not agreeing with the scheduling of project resources and they have asked for your help to determine the resolution. They are refusing to speak with each other and each is telling you that the other person is scheduling project resources for the project that are already scheduled to complete the work. In the communication model, what component represents the disagreement of these two project managers and their refusal to speak with each other about a resolution?
Conflict
Noise
Barrier
Ad hoc
Question 82
Which of the following is responsible to sign off on the closure documents of a project?
Project team members
Project Manager
End user
Sponsor
Question 83
You are the program manager of the NHQ Program for your organization. Your program has 14 constituent projects that are all creating benefits and deliverables for your program. You have recently terminated the GHW Project in your program because you've made trade-offs with other program projects and the deliverables of the GHW Project are no longer affordable. What project management activity should happen in the GHW Project?
Quality audit
Scope verification
Scope control
Financial audit
Question 84
Which of the following documents sets the project objectives?
Project charter
Project schedule
Project scope statement
Project organization chart
Question 85
Who prepares the statement of work (SOW) for external projects?