MB-335 Practice Test

MB-335 Practice Test practice questions, page 6 of 11, with answer review and explanations.

Question 26

A bicycle manufacturing company is implementing Dynamics 365 Supply Chain Management. The warehouse must pick and stage parts other than paint for bicycle assembly. Paint is at the production station. You need to configure the reservations for production. What should you configure? To answer, select the appropriate options in the answer area. NOTE: Each correct selection is worth one point.

Question 27

A manufacturer is implementing Dynamics 365 Supply Chain Management with warehouse management processes (WMS). Warehouse workers use hand-held devices to pick and stage batch-tracked products for production. The warehouse manager requires that products are removed from on-hand inventory and consumed when they are picked and staged for production. You need to remove the products from on-hand inventory. What should you configure?

  1. mobile device menu item, start production order
  2. flushing principle, available at location
  3. flushing principle, start
  4. manufacturing execution, job card device

Question 28

A manufacturer is implementing Dynamics 365 Supply Chain Management to create blends of oil and industrial lubricant. The manufacturer requires detailed documentation for the production order process before manufacturing begins for the products. The shop floor must review, approve, and anticipate all production runs. Before production starts, the manufacturer wants to ensure that the order can be completed by a certain timeframe based on capacity. You need to define the production life cycle stages. Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Question 29

A company uses Dynamics 365 Supply Chain Management. The marketing group needs to be able to view a manufacturer's suggested retail price (MSRP) for a new bill of materials (BOM) item when the cost of the BOM item is calculated. You need to configure the functionality. What should you do?

  1. Set the sales price model field on the calculation group to item sales price.
  2. Use the category price rules to generate a trade agreement with the sales price.
  3. Add a profit setting percentage to a calculation group.
  4. Add a profit setting percentage to the released BOM product.
  5. Add a profit setting percentage to a cost group.

Question 30

A company overstates on-hand raw materials due to the time it takes to post raw materials as consumed when production orders are processed. All items used to manufacture finished goods must be consumed when a finished good is reported as finished. You must not change all bill of materials lines to use the option of flushing principal. You need to ensure that all production orders consume raw materials at Report as finished. Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.