Question 6
While working at the strategy level, the team needs to ensure stakeholders actively support an environment for constructive communication, collaboration, and continuous improvement. They decide to use the following to achieve this goal?
Product Roadmap
Reviews
Behavior driven development
Release Plans
Question 7
The team is very busy working on a top priority initiative. They have delivered many user stories and have many left to complete. However, the components they are delivering are not yet delivering end-to-end business value. How can the team maintain understanding of the big picture without getting lost in the details?
Create a gantt chart
Refine their backlog
Create a story map
Fully elaborate user stories
Question 8
When decomposing stories, the concept of “breadth before depth” signifies progressively breaking down:
Estimates and resources required to accomplish the story
Backlog items to the lowest level of detail upfront
Business goals into user stories representing smaller increments of value
Tests to align with usable functionality delivered through each story
Question 9
The delivery team is in a meeting identifying cycle time improvement opportunities for delivery of the final product. They decide to apply the following technique:
Backlog management
Value stream mapping
Story decomposition
Story mapping
Question 10
The team members are discussing the level of effort that different backlog items are likely to require, and how much effort is available for the next sprint. This is an example of the principle: