Question 36
What are the two MAJOR factors to be considered while deciding risk appetite level? Each correct answer represents a part of the solution. (Choose two.)
The amount of loss the enterprise wants to accept
Alignment with risk-culture
Risk-aware decisions
The capacity of the enterprise's objective to absorb loss.
Question 37
You are the project manager of the GHY Project for your company. You need to complete a project management process that will be on the lookout for new risks, changing risks, and risks that are now outdated. Which project management process is responsible for these actions?
Risk planning
Risk monitoring and controlling
Risk identification
Risk analysis
Question 38
You are the project manager of the HGT project in Bluewell Inc. The project has an asset valued at $125,000 and is subjected to an exposure factor of 25 percent. What will be the Single Loss Expectancy of this project?
$ 125,025
$ 31,250
$ 5,000
$ 3,125,000
Question 39
Which of the following are the principles of access controls? Each correct answer represents a complete solution. (Choose three.)
Confidentiality
Availability
Reliability
Integrity
Question 40
You are the project manager of GHT project. You have selected appropriate Key Risk Indicators for your project. Now, you need to maintain those Key Risk Indicators. What is the MOST important reason to maintain Key Risk Indicators?