Question 31
Which of the following is true for Cost Performance Index (CPI)?
If the CPI > 1, it indicates better than expected performance of project
CPI = Earned Value (EV) * Actual Cost (AC)
It is used to measure performance of schedule
If the CPI = 1, it indicates poor performance of project
Question 32
Which of the following do NOT indirect information?
Information about the propriety of cutoff
Reports that show orders that were rejected for credit limitations.
Reports that provide information about any unusual deviations and individual product margins.
The lack of any significant differences between perpetual levels and actual levels of goods.
Question 33
Ben works as a project manager for the MJH Project. In this project, Ben is preparing to identify stakeholders so he can communicate project requirements, status, and risks. Ben has elected to use a salience model as part of his stakeholder identification process. Which of the following activities best describes a salience model?
Describing classes of stakeholders based on their power (ability to impose their will), urgency (need for immediate attention), and legitimacy (their involvement is appropriate).
Grouping the stakeholders based on their level of authority ("power") and their level or concern ("interest") regarding the project outcomes.
Influence/impact grid, grouping the stakeholders based on their active involvement ("influence") in the project and their ability to affect changes to the project's planning or execution ("impact").
Grouping the stakeholders based on their level of authority ("power") and their active involvement ("influence") in the project.
Question 34
Which of the following is the first MOST step in the risk assessment process?
Identification of assets
Identification of threats
Identification of threat sources
Identification of vulnerabilities
Question 35
Which of the following matrices is used to specify risk thresholds?