CRISC Practice Test practice questions, page 33 of 76, with answer review and explanations.
Question 161
You are the project manager of HWD project. It requires installation of some electrical machines. You and the project team decided to hire an electrician as electrical work can be too dangerous to perform. What type of risk response are you following?
Avoidance
Transference
Mitigation
Acceptance
Question 162
You are the project manager of GHT project. You have implemented an automated tool to analyze and report on access control logs based on severity. This tool generates excessively large amounts of results. You perform a risk assessment and decide to configure the monitoring tool to report only when the alerts are marked "critical". What you should do in order to fulfill that?
Apply risk response
Optimize Key Risk Indicator
Update risk register
Perform quantitative risk analysis
Question 163
One of the risk events you've identified is classified as force majeure. What risk response is likely to be used?
Acceptance
Transference
Enhance
Mitigation
Question 164
You are the project manager of GHT project. You have applied certain control to prevent the unauthorized changes in your project. Which of the following control you would have applied for this purpose?
Personnel security control
Access control
Configuration management control
Physical and environment protection control
Question 165
You are the project manager for BlueWell Inc. You have noticed that the risk level in your project increases above the risk tolerance level of your enterprise. You have applied several risk responses. Now you have to update the risk register in accordance to risk response process. All of the following are included in the risk register except for which item?
Risk triggers
Agreed-upon response strategies
Network diagram analysis of critical path activities