Question 161

You are the project manager of HWD project. It requires installation of some electrical machines. You and the project team decided to hire an electrician as electrical work can be too dangerous to perform. What type of risk response are you following?

  1. Avoidance
  2. Transference
  3. Mitigation
  4. Acceptance

Question 162

You are the project manager of GHT project. You have implemented an automated tool to analyze and report on access control logs based on severity. This tool generates excessively large amounts of results. You perform a risk assessment and decide to configure the monitoring tool to report only when the alerts are marked "critical". What you should do in order to fulfill that?

  1. Apply risk response
  2. Optimize Key Risk Indicator
  3. Update risk register
  4. Perform quantitative risk analysis

Question 163

One of the risk events you've identified is classified as force majeure. What risk response is likely to be used?

  1. Acceptance
  2. Transference
  3. Enhance
  4. Mitigation

Question 164

You are the project manager of GHT project. You have applied certain control to prevent the unauthorized changes in your project. Which of the following control you would have applied for this purpose?

  1. Personnel security control
  2. Access control
  3. Configuration management control
  4. Physical and environment protection control

Question 165

You are the project manager for BlueWell Inc. You have noticed that the risk level in your project increases above the risk tolerance level of your enterprise. You have applied several risk responses. Now you have to update the risk register in accordance to risk response process. All of the following are included in the risk register except for which item?

  1. Risk triggers
  2. Agreed-upon response strategies
  3. Network diagram analysis of critical path activities
  4. Risk owners and their responsibility