Question 6

During vendor selection, you are going to verify and validate the previous performance of all vendors competing for the project. Which activity is going to take place?

  1. Reference check
  2. Vendors pre-selection
  3. Request for Proposal (RFP)
  4. Proposal evaluation

Question 7

Activities in a project are discussed in a Work/Product Breakdown Structure (WBS / PBS) session during the planning phase. Estimations are subdivided through the levels of the product breakdown structure. Which estimation technique is applied?

  1. Comparative
  2. Bottom-up
  3. Top-down
  4. Three point

Question 8

For one of the mission critical applications in a telecom organization data loss cannot be tolerated Which replication mode do you recommend?

  1. Instant replication
  2. Synchronous replication
  3. Asynchronous replication
  4. Semi-synchronous replication

Question 9

As part of the business continuity plan preparations, management wants a site arrangement with the presence of all IT infrastructure, data and a desk for the workers. Which site do you recommend?

  1. Cold site
  2. Warm site
  3. Hot site
  4. Mobile site

Question 10

To safeguard integrity during large financial transactions, an additional control is implemented to prevent individuals from committing fraudulent activities, potentially stealing money for their own benefit. Which integrity control is implemented?

  1. Mandatory vacation / holiday
  2. Rotation of duties
  3. Separation of duties
  4. Need to know