Question 91
According to 'A Guide to the Business Analysis Body of Knowledge', when should the business analyst and an organization actually start requirements allocation?
As soon as a budget has been created
After approval of the requirements
After the project charter
As soon as the solution approach is determined
Question 92
You are working with the project stakeholders to analyze and prioritize their requirements for the project. One of the project requirements is to achieve a high-level of customer satisfaction for the project deliverable. What is the danger in this project requirement?
Achieving customer satisfaction is a risk, as the project manager cannot control how satisfied the customer will be with the project deliverables.
Achieving customer satisfaction is an assumption and should be documented in the project scope.
Achieving customer satisfaction should always map to the quality requirements for the project.
Achieving customer satisfaction is a subjective requirement and entails a high level of risk of being successfully accomplished.
Question 93
You are a business analyst in an organization that has recently embraced business analysis as part of its initiative for new projects. In this organization, there is not an organizational standard for tailoring business analysis duties and expectations. Which one of the following best describes the action you should take to begin business analysis?
Work with the appropriate stakeholders to determine how the business analysis work should be completed.
Define the organizational standard first.
Create a business case for the need of organizational standards for business analysis.
Take charge and begin the business analysis activities, but document your approach to serve as a template for future business analysis initiatives.
Question 94
You are the business analyst for your organization and you're working with the project manager to complete some business analysis activities. The project manager has the authority to approve the requirements based on the short iterations of business analysis activities. What approach of business analysis are you using in this scenario?
Progressive elaboration
Change-driven
Plan-driven
Iterative
Question 95
In a change-driven environment, what's more important than formal communications in regard to effective requirements management?