CBAP Practice Test practice questions, page 18 of 20, with answer review and explanations.
Question 86
You are the business analyst for your organization and are working on organizing the identified requirements for a new solution. Nancy, your assistant in this process, says that these requirements aren't very complex. You agree but add that it's this thing that makes the overall solution complex. What thing adds to the level of complexity among requirements?
Relationships among the requirements
Management in the project
Stakeholders in the project
Cost and schedule constraints
Question 87
Which of the following is an estimate based on past projects to predict the current cost and/or duration of the current project?
Current estimate
Past project cost
Past estimate
Top-down estimate
Question 88
You are the business analyst for a large project for your organization. Your project has 65 stakeholders and this will greatly increase the complexity of the communication in this project. To demonstrate how complex this project and its communication will be, you show the management the number of communication channels in this project. How many channels exist in this project based on the number of stakeholders?
2080
4160
4225
65
Question 89
You are creating a model for your requirements. Which model type categorizes and describes the people who directly interact with a solution?