Question 81
Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?
- Plan Procurement Management
- Control Procurements
- Collect Requirements
- Plan Cost Management
Question 82
Which tool or technique is used to manage change requests and the resulting decisions?
- Change control tools
- Expert judgment
- Delphi technique
- Change log
Question 83
The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:
- Work packages.
- Accepted deliverables.
- The WBS dictionary.
- The scope baseline.
Question 84
In which Knowledge Area is the project charter developed?
- Project Cost Management
- Project Scope Management
- Project Time Management
- Project Integration Management
Question 85
The ability to influence cost is greatest during which stages of the project?
- Early
- Middle
- Late
- Completion