Question 66

Which process in Project Time Management includes reserve analysis as a tool or technique?

  1. Estimate Activity Resources
  2. Sequence Activities
  3. Estimate Activity Durations
  4. Develop Schedule

Question 67

Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring that the opportunity is realized?

  1. Enhance
  2. Share
  3. Exploit
  4. Accept

Question 68

Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:

  1. Expert judgment.
  2. Analytical techniques.
  3. Earned value management.
  4. Group decision-making techniques.

Question 69

The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?

  1. Timing
  2. Methodology
  3. Risk categories
  4. Budgeting

Question 70

When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?

  1. Negative
  2. Zero
  3. Positive
  4. Free