Question 11
Your team switched to using story points for estimation in the last 2 months and their sprints are 2 weeks long. Which chart can definitely help you determine the average effort that the team can deliver during each sprint?
- Velocity Chart
- Cumulative Flow Diagram
- Burnup Chart
- Burndown Chart