Question 11

Your team switched to using story points for estimation in the last 2 months and their sprints are 2 weeks long. Which chart can definitely help you determine the average effort that the team can deliver during each sprint?

  1. Velocity Chart
  2. Cumulative Flow Diagram
  3. Burnup Chart
  4. Burndown Chart