Question 6
Teams using Project A and B currently use their own respective Scrum boards. They must now work together on the same products and issues and in the same sprints. You created a new Scrum board based on this filter: project in (A,B) ORDER BY Rank ASC You must also check two settings to make sure the teams can access and use the new board. Identify the two settings. (Choose two.)
application access of all team members
global permissions of all team members
availability of parallel sprints
sharing on the board sub-filter
sharing on the board filter
project permissions
Question 7
Your team needs a new board that: only shows issues that are actively in progress allows a separate area to prioritize incoming work allows them to release issues from the Done column Identify the correct solution to meet these requirements
Create a scrum board and enable the backlog.
Create a scrum board and configure swimlanes.
Create a kanban board and enable column constraints.
Create a scrum board and configure a quick filter.
Create a kanban board and enable the backlog.
Create a kanban board and configure swimlanes.
Question 8
A team needs a board that meets these requirements: All issues can be moved across the entire workflow on a single view of the board. Issues can be worked in a continuous flow without start and stop dates. Which board configuration meets the requirements?
Kanban board without backlog
Scrum board without parallel sprints
Scrum board with swimlanes
Kanban board with backlog
Question 9
Newly created issues start in the To Do column of your Kanban board. The column has grown too full. Additionally, the team is unable to focus on the prioritized issues they should be working on. Which configuration change will help alleviate both problems?
enable the Kanban backlog
use card colors to distinguish priorities
add the Priority field to the card layout
create a quick filter
Question 10
DEV is a company-managed Kanban project with many statuses. Users should never see issues in Cancelled or Rejected status when viewing their project board. You want to remove the issues from the board but still have them counted in project reports. Identify the approach that satisfies this requirement.
remove the statuses from the project workflow
add a board sub-filter to exclude the two statuses
exclude the two statuses from the board filter
hide the two statuses through a quick filter
create swimlanes for all the statuses except those two