Question 11

What is a primary benefit of asking questions to stakeholders who do not have strong decision authority over project funding, but who do have relevant experience?

  1. It shows them that you are interested in their opinions.
  2. The more data, the better.
  3. It can find requirements or opportunities that are relevant to future discussions.
  4. It shows the decision makers you are taking the initiative to get input from people that they might not have identified for interviews.