Question 11
What is the purpose of scheduling a due date for manual executions in UiPath Test Manager?
- To make sure a user is assigned to the manual execution.
- To track the progress of test cases and ensure the timely completion of manual testing tasks.
- To automatically execute test cases when the due date is reached.
- To make sure that if the date passes without running the test case log, the due date is automatically increased.