Question 11
While creating the Sprint Backlog, the Scrum Team along with the Scrum Master and Product Owner must consider which of the following as inputs?
Length of Sprint, Agreed Actionable Improvements, Done Criteria, Team Calendar.
Assigned Action Items, Business Improvements, Dependencies, Team Calendar.
Length of Sprint, Previous Sprint Velocity, Dependencies, Team Calendar.
Proof of Concept, Previous Sprint Velocity, Done Criteria, Team Calendar.
Question 12
Which of the following methods helps estimate the value provided by projects?
Internal Rate of Return
Net Rate of Return
Present Rate of Return
Estimated Rate of Return
Question 13
Suppose you are a Scrum Master or a Scrum Team that is progressing through Tuckman's model of Group Dynamics. In which of the following stages will you be most actively involved?
Forming
Storming
Norming
Performing
Question 14
The Scrum Master can help the Product Owner update business justification in the Project Vision statement and ensure continuous value justification for projects by facilitating which of the following processes? A) Conduct Daily Standup - B) Groom Prioritized Product Backlog C) Retrospect Project - D) Sprint Deliverables -
B and D
A and Ð’
Ð, B, and С
Only Ð
Question 15
While assisting the Product Owner in developing a Prioritized Product Backlog, the Scrum Master must consider the primary factors on which the Prioritized Product Backlog is based-on. Which of the following are those primary factors? A) Value - B) Dependencies - C) Risk - D) Deliverables -