Question 1
According to SAFe Principle #10, what should the Enterprise do when markets and customers demand change?
- Create an Agile Release Train to focus on value
- Reorganize the network around the new value flow
- Apply development cadence and synchronization to operate effectively and manage uncertainty
- Create a reliable decision-making framework to empower employees and ensure a fast flow of value
Question 2
Which statement is true about ART events?
- ART events run inside the team events, and the team events create a closed-loop system
- Team events run inside the ART events, and the ART events create a closed-loop system
- The Inspect and Adapt is the only ART event required to create a closed-loop system
- The daily stand-up is an ART event that requires the scrum of scrums and Program Owner sync involvement in the closed-loop system
Question 3
Which role serves as the servant leader for the Agile Release Train?
- Business Owner
- Release Train Engineer
- Agile Coach
- Scrum Master
Question 4
During the PI Planning event, when are planning adjustments agreed upon?
- During breakout sessions
- During the draft plan review
- During the management review and problem-solving
- During Scrum of scrums
Question 5
What is part of the role of the Scrum Master?
- To escalate ART impediments
- To prioritize and identify what is ready for Iteration Planning
- To facilitate all team events
- To coach the interactions with the Scrum Framework