Question 21

Which metrics will help a Product Owner determine if a product is delivering value? (Choose two.)

  1. Productivity.
  2. Time to market.
  3. Velocity.
  4. Percentage of scope implemented.
  5. Customer satisfaction.

Question 22

Every Scrum Team should have: (Choose the best answer.)

  1. One Lead Developer and no more than 8 other members.
  2. The competencies and skills needed to deliver an Increment in a Sprint.
  3. At least one representative from each major department, such as, Quality Assurance, Development, and Marketing.

Question 23

A product's success is measured by: (Choose three.)

  1. The impact on my performance rating.
  2. The impact on revenue.
  3. The impact on customer satisfaction.
  4. The impact on cost.
  5. The impact on my boss's mood.
  6. The delivery of upfront defined scope compared to the upfront planned time.

Question 24

Scrum is based on empiricism. All of its artifacts must be transparent to ensure sufficient accuracy of inspection. How can the Scrum Team maintain the Product Backlog to maximize its transparency? (Choose the best answer.)

  1. Product Backlog items must be sized such that the highest ordered items are no bigger than a Sprint.
  2. The Product Backlog is continually kept up to date with the most recent insights.
  3. The Product Backlog is only updated at the Sprint Review, when both the Scrum Team and the stakeholders are available.
  4. The Product Backlog is only updated at a release planning meeting with the stakeholders and the change control board present.
  5. Product Backlog items should hold no more than 8 points of work, which is the average in the range of acceptable sizes of 1, 2, 3, 5, 8, and 13.

Question 25

True or False: The Product Owner makes sure the correct stakeholders are invited to the Sprint Retrospective. They might have important instructions for team improvements.

  1. True
  2. False