Question 11

True or False: An Increment must be released to customers or users at the end of each Sprint.

  1. True
  2. False

Question 12

A Product Backlog is: (Choose three.)

  1. Ordered based on priority, value, dependencies, and risk.
  2. Only visible to the Product Owner and stakeholders.
  3. An inventory of things to be done for the Product.
  4. An exhaustive list of upfront approved requirements to be implemented.
  5. Managed by the Product Owner.

Question 13

Why does the Product Owner want the Developers to adhere to its Definition of Done? (Choose the best answer.)

  1. To be able to reprimand the team when they do not meet their velocity goal for the Sprint.
  2. To predict the team's productivity over time.
  3. To have complete transparency into what has been done at the end of each Sprint.
  4. To know what the team will deliver over the next three Sprints.

Question 14

Which statement best describes the Sprint Backlog as the output of the Sprint Planning? (Choose the best answer.)

  1. Every item has a designated owner.
  2. It is ordered by the Product Owner.
  3. Each task is estimated in hours.
  4. It is the Developers plan for the Sprint.
  5. It is a complete list of all work to be done in a Sprint.

Question 15

Which is NOT a valid consideration when ordering a Product Backlog? (Choose the best answer.)

  1. Importance to customers.
  2. Tools and techniques.
  3. Alignment with business strategy and goals.
  4. Risk.
  5. Dependencies on other Product Backlog items.