Question 26

Stakeholders are only allowed to meet with the Scrum Team at Sprint Review.

  1. True
  2. False

Question 27

Which Scrum Value is impacted by trust?

  1. Respect
  2. Courage
  3. Commitment
  4. Openness
  5. Focus
  6. All of the above

Question 28

Doing your best and helping other Scrum Team members demonstrates which of the following?

  1. Value of Commitment
  2. Increased Revenue
  3. Increased Profit
  4. Maximizing utilization
  5. High Performance

Question 29

Peter, a Project Manager, has raised concerns about your Scrum Team's productivity and progress towards the objectives. Which is the best way to respond to Peter's concerns?

  1. Share the Product Backlog, the projections towards the release dates and ensure that Peter has access.
  2. Show the Profit & Loss (P&L) report.
  3. Share the current impediments.
  4. Share the last stakeholder status report prepared by the Scrum Master.

Question 30

The three pillars of empirical process control consist of:

  1. Planning, Inspection, Adaptation
  2. Inspection, Transparency, Adaptation
  3. Planning, Demonstration, Retrospective
  4. Respect For People, Kaizen, Eliminating Waste