Question 46

Which of these may a Development Team deliver at the end of a Sprint?

  1. Failing unit tests, to identify acceptance tests for the next Sprint.
  2. An increment of software with minor known bugs in it.
  3. An increment of working software that is ג€doneג€.
  4. A single document, if that is what the Scrum Master asked for.

Question 47

How much of the Sprint Backlog must be defined during the Sprint Planning event?

  1. Just enough tasks for the Scrum Master to be confident in the Development Team's understanding of the Sprint.
  2. The entire Sprint Backlog must be identified and estimated by the end of the Sprint Planning meeting.
  3. Enough so the Development Team can create its best forecast of what is can do, and to start the first several days of the Sprint.
  4. Just enough to understand design and architectural implications.

Question 48

Who is responsible for managing the progress of work during a Sprint?

  1. The Scrum Master.
  2. The Development Team.
  3. The Product Owner.
  4. The most junior member of the Team.

Question 49

A Development Team is required to deliver a done Increment by the end of a Sprint. Select two statements that explain what `Done` means. (Choose two.)

  1. All work the Development Team is willing to do.
  2. Ready for integration.
  3. No work left from the definition of ג€Doneג€.
  4. Whatever the Product Owner defines as quality.
  5. Ready to be released to end users.

Question 50

What two factors are best considered when establishing the Sprint length? (Choose two.)

  1. The organization has mandated similar length sprints.
  2. The level of uncertainty over the technology to be used.
  3. The frequency at which team formation can be changed.
  4. The risk of being disconnected from the stakeholders.