Question 101
Which is a recommended quality review team role?
Project Manager
Assurance
Project Support
Administrator
Question 102
Which is a recommended quality review team role?
Project Manager
Assurance
Chair
Producer
Question 103
Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.
controls
products
project management team
stages
Question 104
Which is a purpose of a Project Product Description?
Records the costs and timescales for delivery of the project's final product
Shows the dependencies between the project's products to aid planning
Provides a list of all the products to be delivered by the project
Defines what the project must deliver in order to gain acceptance
Question 105
Which of the following statements about quality assurance and Project Assurance is true?
Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project Board
Project Assurance is independent of the Project; quality assurance is only independent of the Project Manager
Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project Board
Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization