PRINCE2 Agile Foundation Cheatsheet
PRINCE2 Agile Foundation
Download free PDFAgile mindset, people and culture
Being agile and doing agile
- **Agility** is the ability to embrace and respond to change. **Being agile** means adaptive thinking, collaboration and learning; **doing agile** means applying practices such as boards, timeboxes and reviews.
- The **Agile Manifesto** values individuals and interactions, working software, customer collaboration and responding to change over processes and tools, comprehensive documentation, contract negotiation and following a plan. The latter still have value.
- The **Agile Onion** moves inward from processes and practices to principles, values and mindset. Visible ceremonies need supporting beliefs; principles explain why practices are useful.
- **Iterative** work refines understanding through repeated feedback. **Incremental** delivery adds usable capability in portions. **Empiricism** bases decisions on observation and experience; inspect results and adapt.
Behaviours and rich communication
- **Transparency** makes real status and problems visible. **Collaboration** builds shared goals and ownership. **Self-organization** lets teams decide how to work within agreed boundaries.
- **Rich communication** uses an effective, interactive channel with rapid feedback. Face-to-face discussion, shared visuals and demonstrations help resolve ambiguity; distributed teams can use video and shared boards.
- **Exploration** uses experiments and stakeholder feedback to discover better solutions. Learn through small, controlled steps rather than specifying every detail before learning is possible.
- An **information radiator** makes useful information easy to see without requesting a report. Keep boards current, understandable and accessible to the intended audience.
Safety, leadership and working agreements
- **Culture** consists of shared attitudes, values and goals. **Co-creation** involves affected people in shaping solutions and ways of working, strengthening understanding and adoption.
- **Psychological safety** supports speaking up: **inclusion** means belonging; **learner** safety supports questions and mistakes; **contributor** safety supports applying skills; **challenger** safety supports questioning the status quo.
- **Team working agreements** are created together: decide communication habits, availability, decision rules and how to handle conflict. Revisit them as the team learns.
- **Delegation poker** helps a team discuss and agree decision authority. Clear delegation supports autonomy; leaders provide purpose, remove obstacles and model learning.
- **Agile sustainability** needs a maintainable pace and continuous improvement. Gain leadership support by connecting agility to business outcomes, value and risk; assess maturity and support people through organizational change.
Projects, products and business as usual
- A **project** is temporary and delivers agreed products to support change. **Business as usual (BAU)** is ongoing operation, service or maintenance, often performed by established teams. Both can use agile techniques.
- **PRINCE2 Agile** blends project governance with agile ways of working. PRINCE2 supplies direction and management; approaches such as Scrum and Kanban support delivery. Agile is not limited to IT.
- **Waterfall** organizes development into sequential phases with distinct goals. Agile uses short feedback cycles to refine requirements and deliver incrementally.
- **Scaling** coordinates multiple teams, dependencies and decisions around shared outcomes. Align terminology, product priorities and governance; inconsistent language and culture can obstruct the blend.
Principles, governance and responsibilities
Seven principles in an agile setting
- **Continued business justification** keeps the investment worthwhile as scope evolves. **Learn from experience** uses feedback, reviews and retrospectives throughout the work.
- **Defined roles, responsibilities and relationships** connect business, user and supplier interests. **Manage by stages** creates decision points for continued investment; stages can contain several releases or iterations.
- **Manage by exception** delegates authority using tolerances and escalates forecast breaches. **Focus on products** defines intended outputs and acceptance before planning activities.
- **Tailor to suit the project** adapts controls, information and working practices to context. Preserve the principles while adjusting emphasis and detail; use suitability assessments to guide tailoring.
Direction, management and delivery
- **Commissioning** establishes the business mandate and overall constraints. The **project board** directs and authorizes; the **project manager** manages the project day to day within delegated limits.
- **Delivery teams** organize specialist work within agreed work packages and constraints. Local autonomy works alongside accountability, visibility and escalation.
- The **organization** practice establishes accountability and responsibility. **Project assurance** independently checks business, user and supplier interests; **project support** assists with administration, information and controls.
- The integrated elements are **principles, people, practices, processes and project context**. People include those doing the work and those affected; practices address recurring management concerns; processes organize lifecycle activity.
Business, user and supplier interests
- The **executive** owns the business case and balances business, user and supplier demands, keeping the project focused on value for money.
- The **senior user** represents user needs, acceptance and expected benefits. The **chief product owner** aligns user priorities and product owners across the project.
- The **senior supplier** represents those designing, building or supplying products and safeguards technical integrity, feasibility and the availability of supplier resources.
- **Stakeholders** can affect or be affected by the project. Identify their needs, influence and engagement requirements; operational staff and external parties can matter even without formal project roles.
Product and delivery roles
- The **product owner** manages and orders the product backlog to maximize value, clarifies user needs and supports acceptance. A backlog role does not automatically confer project-board authority.
- The **team manager** coordinates delivery against agreed work packages. **Developers** create specialist products; **testers** help evaluate quality and expose defects throughout development.
- The **team coach** helps a team improve collaboration and delivery practices; the **agile coach** supports wider adoption and capability. In Scrum, the **Scrum Master** coaches, facilitates effectiveness and helps remove impediments.
- **Customer representatives and customer subject matter experts** clarify user needs and business detail. **Supplier representatives and supplier subject matter experts** contribute technical expertise, constraints and standards compliance.
Fixed targets and flexible delivery
- The **fix and flex** approach protects time and cost while allowing scope to vary. Agreed quality criteria can have tolerances; essential quality is protected. Risk and benefits remain subject to agreed governance.
- **Be on time and hit deadlines** supports confidence and dependency planning. **Protect the level of quality** preserves fitness for purpose: plan testing and verification into delivery.
- **Embrace change** by accommodating useful learning within boundaries. **Keep teams stable** to preserve knowledge, relationships and predictable capacity; adding people late can disrupt delivery.
- **Accept that the customer does not need everything**: prioritize valuable, essential capability and defer lower-value features. A smaller usable product can deliver benefits sooner.
- **Tolerance** is permitted variation around an objective. If a forecast exceeds delegated limits, escalate before the breach. Fixed time and cost make delivered scope and remaining benefits especially important signals.
Value, requirements and planning
Business case and product vision
- The **business case** justifies investment through expected benefits, costs and risks. Reassess desirability, viability and achievability as delivery reveals new information.
- An **output** is a delivered product; an **outcome** is the resulting change; a **benefit** is a measurable improvement. Delivering features does not by itself prove that benefits were realized.
- Define the **minimum viable product (MVP)** and its role in learning or benefit delivery. Identify when it is expected and how reduced scope could affect the business case; an MVP is not the entire viability argument.
- **Personas** express relevant user needs, goals and contexts to help articulate benefits. **Objectives and key results (OKRs)** connect a clear objective to measurable results.
- The **project product description** gives the overall product vision, purpose and acceptance expectations. A **project canvas** concisely aligns purpose, value and key project information; revisit it at decision points and closure.
Backlogs, epics and user stories
- A **backlog** is an ordered list of work or requirements. The **project backlog** expresses major project products, often as epics; **product backlogs** contain product requirements; a **sprint backlog** captures selected work and its delivery plan.
- An **epic** is a broad, high-level user story that needs decomposition. A **user story** expresses who needs what and why, commonly: As a [user], I want [capability], so that [benefit].
- **Refinement** adds detail, splits work, estimates effort and clarifies priority as understanding develops. Near-term items need more detail than distant items.
- **Acceptance criteria** specify testable conditions for a particular story or product. They become clearer through conversation; a story is a prompt for shared understanding, not a complete specification by itself.
MoSCoW and trading scope
- **Must have** is essential for a viable delivery; **Should have** is important but can be deferred with difficulty; **Could have** is desirable; **Won't have this time** is explicitly outside the current commitment.
- Apply **MoSCoW** to a stated horizon such as a release or timebox. If everything is a Must, there is little room to absorb uncertainty; identify a useful minimum and genuine flexibility.
- **Trading or swapping** replaces lower-priority work with new work of comparable effort within agreed constraints. Check dependencies, quality, risks and benefits before accepting the trade.
- **Scope** concerns what capability is delivered; **quality** concerns its required characteristics and fitness for purpose. Distinguish functional features from non-functional needs such as performance and security when prioritizing.
Product planning and delivery horizons
- The **plans** practice defines products, their delivery approach, responsibilities, timing and resources. **Product-based planning** begins with required products and descriptions, then identifies dependencies and activities.
- Use **project, stage and team plans** at appropriate detail. High-level plans coordinate outcomes and dependencies; detailed team planning adapts through evidence rather than pretending all future work is certain.
- A **release map or release plan** shows intended increments, sequence and dependencies. Establish an initial view during initiation and refine it as learning changes priorities.
- A **management stage** is a governance interval; a **release** makes capability available; an **iteration or sprint** is a delivery cycle. They are different boundaries and need not coincide.
- **Gantt charts** can show project milestones and dependencies. Backlogs and boards help teams plan detailed work. Choose a representation that supports the decision and keep plans consistent across levels.
Timeboxes, estimates and learning
- A **timebox** is a fixed period for work toward a goal. Timeboxes can be nested; a release may contain several iterations. Protect the endpoint by managing content and capacity.
- **Story points** estimate relative size, complexity and uncertainty; **T-shirt sizing** uses broad categories such as S, M and L. Team estimates support conversation rather than promising exact elapsed time.
- **Velocity** is the amount of work a team completes per iteration, commonly in story points. Use that team's history to inform forecasts; compare like work and avoid treating velocity as an individual productivity score.
- A **spike** is time-limited investigation to reduce uncertainty. **Lean Startup** uses build-measure-learn and an MVP to test assumptions with minimal effort, then adapt based on evidence.
Quality, risk and change control
Quality, Ready and Done
- The **quality** practice defines what makes products fit for purpose and how this will be verified. Capture user expectations early and translate them into measurable acceptance and quality criteria.
- **Definition of Ready (DoR)** describes when an item is sufficiently understood to start: clear need, measurable acceptance criteria, manageable size and understood dependencies.
- **Definition of Done (DoD)** is the shared completion standard, such as completed development, testing and required documentation. **Acceptance criteria** concern the individual item; DoD applies consistently across work.
- Build quality into each increment. Address minor control failures by revisiting development and tests; escalate according to impact and authority. **Refactoring** improves internal structure while preserving intended behavior.
- **Quality tolerance** permits agreed variation in a criterion. Prioritize criteria explicitly; do not meet a deadline by silently dropping essential tests, documentation or acceptance requirements.
Risk management and agile suitability
- A **risk** is an uncertain event that could affect objectives, positively or negatively. Risk management should be proportionate; agile feedback reduces some uncertainties but does not remove the need for risk control.
- **Identify** risks; **assess** probability, impact and overall exposure; **plan** responses; **implement** them and monitor effectiveness. Communicate throughout and give risks and responses clear owners.
- The **risk management approach** defines how risks are handled; the **risk register** records individual risks and responses. Include adoption, delivery, dependencies and transition risks.
- The **Agilometer** assesses suitability and risks of agile working. The project manager facilitates an early assessment and repeats it as conditions change; use each area to guide improvements rather than averaging away weaknesses.
- Its areas cover **scope flexibility, collaboration, communication, iterative and incremental capability, environmental conditions and acceptance of agile**. An **enterprise agility assessment** considers adoption across the wider organization.
Issues, changes and delegated decisions
- An **issue** is something requiring management attention now; a risk concerns uncertainty. Capture the issue, assess impact and options, recommend action, obtain the appropriate decision and implement it.
- The **issues** practice controls changes affecting approved baselines. **Change control** evaluates consequences for products, plans, benefits, cost, risk and quality before committing.
- Authorize teams to manage emerging detail and trade work within agreed boundaries. A change to an approved baseline or beyond delegated tolerance follows the appropriate governance route.
- Keep decisions and product versions traceable. Frequent releases increase the importance of **configuration management**, clear ownership and consistent records of what was built, tested and released.
Processes and collaborative workshops
Starting, directing and initiating
- **Starting up a project** checks whether there is a worthwhile basis to initiate. Establish initial roles, lessons, project brief and an initiation plan without unnecessary detailed design.
- **Directing a project** is the board's decision-making process across the lifecycle: authorize initiation, delivery stages and closure, and give direction when needed. The board manages by exception.
- **Initiating a project** establishes a sound foundation: business case, project plan, management approaches, roles and controls. Agree how agile delivery, releases, quality and reporting will work.
- **Starting up, kickoff and initiation workshops** build shared understanding of purpose, roles and working arrangements. **Agile enablement workshops** address readiness, adoption risks and common delivery standards, including Ready and Done.
Controlling stages and delivering products
- **Controlling a stage** is the project manager's cycle of authorizing work, reviewing progress, handling risks and issues, taking corrective action and reporting to the board.
- **Managing product delivery** controls the agreement between project management and delivery: accept a work package, execute the work, and deliver products meeting the agreed requirements.
- A **work package** communicates required products, quality expectations, constraints, reporting and acceptance arrangements. Agree what delivery involves before the team commits.
- **Team planning workshops** clarify goals and select achievable work. **Progress review workshops** inspect status, obstacles and forecasts. Keep team-level information connected to stage-level decisions.
Stage boundaries, closure and handover
- **Managing a stage boundary** reviews stage performance, updates the business case and project plan, and prepares the next stage plan so the board can decide whether to continue.
- **Release planning and release review workshops** can support stage-boundary decisions by revisiting priorities, dependencies, delivered value and plans for further work.
- **Closing a project** confirms acceptance, reviews performance and lessons, and transfers remaining responsibilities. Plan benefits reviews and follow-on actions for anything outstanding.
- **Project closure workshops** consolidate outcomes and lessons. Update the project canvas and relevant records, confirm ownership and prepare the operational handover.
- **Transition to operations** needs clear functionality and support documentation, training, ownership and applicable service levels. Maintain feedback loops, suitable KPIs and accessible work information for ongoing improvement.
Facilitating useful workshops
- A **workshop** is a collaborative, facilitated event with a defined purpose and outputs. Invite the right participants, prepare inputs, timebox discussion and record decisions and actions.
- Well-run workshops build **consensus and ownership** through shared understanding. Use them for problem solving, requirements, planning, personas and alignment; include differing stakeholder perspectives.
- A **review** inspects the product and obtains feedback. A **retrospective** inspects how people worked and selects improvements. Choose a few valuable actions for the next cycle and check whether they helped.
- **Glad! Sad! Mad!** is a retrospective prompt for experiences and feelings. Combine these signals with evidence, use a safe atmosphere and focus on improvement rather than blame.
Delivery approaches, progress and feedback
Scrum, Kanban and Lean
- **Scrum** is an iterative, incremental framework using fixed-length sprints. **Sprint planning** agrees the goal, achievable work and delivery approach; the **Daily Scrum** inspects progress toward the goal and adapts the plan.
- A **Sprint Review** inspects the increment with stakeholders and considers what to do next. A **Sprint Retrospective** improves effectiveness and quality. An **increment** is usable work meeting the Definition of Done.
- **Kanban** visualizes workflow, limits **work in progress (WIP)** and improves flow. Pull new work when capacity exists; expose bottlenecks and help finish work before starting more.
- **Lean** emphasizes customer value, reduced waste and smooth flow. **Swarming** brings several people together to finish or unblock an item. Flow-based work does not require sprint boundaries.
Progress, reports and dashboards
- The **progress** practice compares actual results with plans, forecasts future performance and supports control of deviations. In agile delivery, emphasize completed products and remaining scope, alongside time and cost.
- A **checkpoint report** communicates team or work-package progress to the project manager. A current team board and conversations can supply the information when they satisfy agreed reporting needs.
- A **highlight report** summarizes stage status, forecasts, risks and issues for the project board at agreed intervals. A forecast tolerance breach requires exception handling rather than waiting for the next routine report.
- **Team dashboards** show delivery flow and detail; **project dashboards** summarize value, milestones and overall health. Information radiators can let managers pull current information, with clear escalation for decisions.
Burn charts and evidence of progress
- A **burn-down chart** plots remaining work against time; a **burn-up chart** plots completed work and can show a separate total-scope line. Scope changes are easier to see when shown explicitly.
- The **ideal line** is a planning reference; the actual line is evidence. Flat remaining work, slow completion or rising scope prompts investigation and a revised forecast.
- Charts need consistent units, reliable completion criteria and context. Elapsed time or hours spent does not prove usable delivery; count work according to the agreed completion standard.
- Use **velocity**, WIP, lead time and cycle time to inform improvement. **Lead time** follows work from request to delivery; **cycle time** measures elapsed time through the defined active workflow.
Frequent releases and informed adaptation
- **Frequent releases** bring earlier value and real-user feedback, reduce batch size and improve handover experience. Maintain customer involvement, quality controls and configuration discipline.
- A **staging area** permits validation, integration or regulatory checks before operational use. Completing an increment, releasing it and placing it into live use are distinct events.
- **Product management** continues across the product lifecycle, beyond project closure. Keep prioritizing value, measuring outcomes and learning from operation through ongoing feedback.
- **AI support** can help summarize information, detect patterns and provide forecasts that inform iterative decisions. Validate inputs and outputs; accountable people still make governance, quality and release decisions.