Question 61
In the beginning of project execution, the project manager finds out that a key resource will be unavailable for two weeks, which could cause a delay to the schedule.What should the project manager do first?
Assign the tasks to another resource, and ask the resource to work double shifts
Update the schedule to reflect the project’s changes in duration
Ask human resources (HR) for a replacement, and update the risk register
Update the resource management plan and resource allocation chart accordingly
Question 62
A project manager is managing an innovation project for a big corporation. The project manager is planning to use email as the main communication channel; however, the product owner prefers to use another approved communication tool instead of email.What should the project manager do?
Contact the sponsor to request direction regarding the communication tool to be used by the project team
Update the communications management plan based on the product owner’s preferences and distribute to the team
Suggest to the team to start using the communication tool suggested by the product owners
Request the product owner to use email because using another tool will increase the workload
Question 63
The customer's project manager changes during the final stage of a project.How can the project manager avoid a project closure delay?
Update the stakeholder engagement plan
Review the latest project status report and update the stakeholders
Escalate the case to the customer's management team
Issue the project payment invoice to the customer in advance
Question 64
During project execution, a conflict occurs between the project manager and one of the team members at every project team meeting. The ongoing conflict is preventing tasks and deliverables from being completed. The project manager contemplates changing their leadership style.What should the project manager do?
Review the set of responsibilities with the team member
Avoid the team member to prevent further conflicts
Escalate the situation to the project sponsor
Review the personnel skill documents
Question 65
During the course of a project, the project manager's immediate director is communicating directly with the client to approve changes without the project manager's knowledge. This is causing confusion in the project team where the scope is changing in the background, but only being mentioned in project meetings.How should the project manager handle this?
Communicate directly with the director and inform them of the communications management plan
Communicate directly with the client stating that any scope changes must go through the project manager
Review the stakeholder engagement plan and put in place any existing actions accordingly
Discuss the issues with the project team and let them know that the project manager will handle scope changes