Question 51
You have been hired as a project manager for Tech Perfect Inc. You are studying the documentation of planning of a project. The documentation states that there are twenty-five stakeholders with the project. What will be the number of communication channels for the project?
300
50
600
25
Question 52
You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project, which has caused you to spend $2,073,654. What is this project's schedule variance?
-$48,654
13 percent
-$225,000
0.98
Question 53
The figure given below demonstrates the communication model for a project. What role does the component E play in the communications model?
Static
Deterrent
Noise
Barrier
Question 54
Which of the following documents is a narrative description of products or services to be supplied by the project and has detailed requirements and pricing specified on it?
Scope of statement
Project charter
Statement of work (SOW)
WBS
Question 55
Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned. What is the cost variance for this project that Fred needs to report to management?