PMI-RMP practice questions, page 9 of 18, with answer review and explanations.
Question 41
As part of identifying the risk appetite of project stakeholders, the project manager must first identify the stakeholders. Which of the following inputs are used to identify project stakeholders?
Project charter, management reserve, enterprise environmental factors, and organizational process assets
Project management plan, human resource plan, enterprise environmental factors, and organizational process assets
Project charter, bid documents, enterprise environmental factors, and organizational process assets
Project charter, communications management plan, enterprise environmental factors, and organizational process assets
Question 42
After applying several risk identification techniques, the risk manager is ready to document project risks in the risk register, including risk name, risk statement, probability of occurring, and potential impact. After this information is complete, who is best suited to serve as risk owners?
Risk manager
Project sponsors
Project manager
Project team members
Question 43
Which of the following should the risk manager consider as external environmental factors when creating the risk management plan?
Government regulations, industry best practice templates, organizational standard processes, and competitor landscape
Government regulations, industry standards, conditions of the marketplace, and competitor landscape
Government regulations, risk categories, organizational standard processes, and competitor landscape
Government regulations, human resource policies and procedures, organizational standard processes, and competitor landscape
Question 44
Within the organizational process assets, where would the project manager find risk response effectiveness from past projects?
Change management plan and lessons learned
Stakeholder register and lessons learned
Risk audit and lessons learned
Risk audit and risk matrix
Question 45
Which analysis method uses stratified sampling without replacement?