PMI-RMP practice questions, page 5 of 18, with answer review and explanations.
Question 21
In what way can the risk manager determine when poor risk planning techniques are influencing the scope, schedule, quality, and/or budget of the project?
Evaluate the results of the Monte Carlo analysis
Document and periodically update project risk information
Monitor project metrics and performance information
Update the risk management plan
Question 22
The company board is concerned about potential legal action from a high-risk project What technique can be used to justify risk response decisions taken on this project?
Interviews
Nominal group technique
Brainstorming
Decision tree analysis
Question 23
The project manager generates a monthly risk report for key stakeholders which documents high and medium risk items only. Where would the project manager find the list of recipients for the report?
Communications management plan
Risk management plan
Risk register
Project charter
Question 24
A CEO wants to reduce costs in the time spent for risk management activities. What step did the risk manager fail to perform?
Assigning the CEO as a risk owner
Preventing all issues from occurring
Properly communicating the risk management activities and their outcomes
Explaining the purpose of the management reserve
Question 25
A risk on the risk register is triggered. This triggered risk costs US$200,000 to mitigate and will overwhelm the project, causing it to fail if not mitigated. The project manager identifies that there is US$200,000 left in the management reserve. From which of the following sources should the funds be drawn to cover the risk mitigation?