Question 11

A risk is identified and documented by the risk manager, but it is unclear how this risk can be proactively managed. In this situation, what type of reserve should be allocated for the risk?

  1. Contingency
  2. Management
  3. Budget
  4. Residual

Question 12

Which of the following is an effective channel for risk mitigation assistance, project risk visibility and risk escalation support?

  1. Project steering committee
  2. Project management office (PMO)
  3. Change control board (CCB)
  4. Board of directors

Question 13

The risk manager wants to determine what is to be measured, how it is to be measured, and what project outcomes are to be measured. In which of the following processes should this be established?

  1. Initiating Process
  2. Executing Process
  3. Planning Process
  4. Monitoring and Controlling Process

Question 14

Which of the following are examples of relevant data gathering tools?

  1. Risk response plan and interviews
  2. Questionnaires and historical data
  3. Work breakdown structure and historical data
  4. Work breakdown structure and interviews

Question 15

The risk manager is conducting stakeholder analysis. Which technique should be used to help identify and manage expectations?

  1. SWOT analysis
  2. Influence diagram
  3. Power/Interest Grid
  4. Interactive method