Question 81
While creating the appropriate risk strategy, the project manager discovers that the project team lacks the necessary expertise to define the risk management plan. What additional resources should be utilized?
Consultants, organizational process assets, subject matter experts, and stakeholder tolerance analysis
Consultants, industry group, and subject matter experts
Consultants, professional and technical associations, subject matter experts, and industry groups
Consultants, professional and technical associations, and subject matter experts
Question 82
A project manager is creating a risk management plan, but participants in a group meeting are hesitant to express their concerns. What will encourage participants to offer their opinions?
Brainstorming
Monte Carlo simulation
Interviews
Nominal group technique
Question 83
Which of the following is a key element of neuro-linguistic programming?
Re-coding based on agile methodology
Flex-scheduling
Cross-training
Building rapport with others
Question 84
When monitoring the execution quality of risk-related plans and processes, which of the following would be a useful metric to track and record?
The number of risks in the project risk register
The degree of variation from the baseline
The number of levels in the risk breakdown structure
The degree of variation from the risk response strategy
Question 85
A project manager identifies a risk in a multifunctional project and decides to take no action. What should the risk manager do if the risk occurs?