Question 66
The project manager is implementing a computer interface to facilitate communications between two ticketing systems for two major companies in the IT industry. During the Plan Risk Response process, the project team agrees on the contingency plan that should mitigate the negative impact of the risk. However, during the project execution, one of the subject matter experts identifies a residual risk that was not taken into consideration during the risk response planning session, but could potentially affect the project schedule baseline. What should the risk manager do to handle this residual risk?
Increase the management reserve.
Analyze this risk and update the risk register.
Accept the risk, since it is minor.
Reject the risk, since the risk plan will take care of all the risks.
Question 67
The risk management process can be defined as which of the following?
Iterative through the planning phase
Baselined at the beginning of execution
Iterative throughout the entire project
Updated in the execution phase
Question 68
A risk manager creates a survey for project stakeholders to obtain their opinions on high levels of risk. Key questions in the survey address acceptable levels of cost increases and schedule delays. What is the risk manager trying to determine?
Risk urgency
Risk exposure
Risk threshold
Risk attitude
Question 69
Which of the following will ultimately determine risk thresholds?
The absolute value of the consequence
The risk appetite of the key stakeholders
The practice standard for risk management
The project manager
Question 70
Which of the following represents levels of risk attitude?