Question 11
A new team member asks what changes could accelerate a change to the project plan. What should be the proper response?
Competitors joined forces with the team
The customer changed requirements
Project team members obtained additional certifications
Technology which did not interfere with the final product
Question 12
Midway through an iteration, an agile team learns that a team member will be unavailable for the next two iterations. As a high-performance team, what should the team do?
Raise an impediment that resource tasks will be blocked and notify the product owner
Ask the delivery manager for a temporary resource
Ask the scrum master to assign that team member's tasks to the next available resource
Assume the team member's tasks to meet iteration goals, and notify the product owner
Question 13
An agile practitioner wants to ensure that stakeholders have current information about a project's progress. What should the agile practitioner do?
Regularly circulate an updated, detailed version of the project plan
Frequently update the online project management office (PMO) repository site
Invite the stakeholders to daily stand ups
Post a project board in an area where all can view it
Question 14
A company has decided to combine two similar products consisting of multiple teams into one product. Engaged customers want to know how the company is looking at re-organizing its teams. What strategy should be employed to re-organize the teams?
All the teams from both products should be simultaneously called together and allowed to completely self-manage
Teams that worked on similar components in the separate products should be combined to minimize disruption and capitalize on synergies
After grouping individuals by role, multi-discipline teams should be created that are comprised of one member from each role
Features should be prioritized and then teams should be organized around those priorities
Question 15
A client states that a product is not being built as requested. How should the agile team address this?
Conduct an internal review to validate functionality before shipping
Audit the quality control process to ensure that the product adheres to requirements
Lengthen iterations to ensure there is sufficient time to build functionality
Hold product review sessions with the client to obtain product acceptance