PK0-005 Practice Test practice questions, page 24 of 25, with answer review and explanations.
Question 116
A project manager is working on a project charter and has successfully documented the project objectives and the success criteria. Which of the following should the project manager define NEXT to complete the project charter?
Proposed solution design
Preliminary scope statement
Responsibility assignment matrix
Initial budget baseline
Question 117
A project has been initiated to provide insurance forms for a company. A constraint for this project is that the insurance commission in each state where the company underwrites has to approve each form. Which of the following compliance considerations BEST describes this scenario?
Regulatory impacts
Environmental impacts
Organizational impacts
Sensitive data types
Question 118
During the execution of production for a bike, a PM was hired. One month later, the PM has been receiving multiple project report requests from stakeholders. Which of the following should the PM do FIRST?
Discuss the requests with the sponsor.
Prepare and send the information.
Assign this task to the project team.
Review the communication plan.
Question 119
A team member finds a malfunctioning procedure in the system that will take a considerable amount of time to fix. Which of the following should be done FIRST?
Update the risk register
Document the finding in the change log.
Create a record in the issue log
Detail a proposed solution.
Question 120
A project team has identified a bug during user acceptance testing. Which of the following is the BEST method for communicating that bug to the development team?
Call the development lead to discuss the fixes for the bug.
Include the bug issue as part of the status update for stakeholders.