Question 101
Which of the following is a typical characteristic of Scrum?
Large teams
Low-risk scope
Self-organized team
Well-defined scope
Question 102
In the kickoff meeting, a project manager announced the project will use a tool to store documents, artifacts, and any other data relevant to the project. The tool will perform version control, maintain retention data, and archive destruction or historical information. Which of the following is being described?
Record management system
Project dashboard
Backlog
Wiki knowledge base
Question 103
Which of the following key project elements is used to organize deliverables into manageable pieces to ensure the proper steps are executed and to achieve the project's core objectives?
WBS
RACI
RFP
PERT
Question 104
After a meeting, a team member recaps all of the topics that worked well, worked relatively well, and did not work at all. The expectation is for upcoming project work to make better progress and achieve targets. Which of the following combinations of tactics is being used?
Stand-up meeting, action items
Workshop meeting, timeboxing
Status meeting, follow-ups
Presentation meeting, meeting notes
Question 105
In the middle of a five-year project, a vendor asked the buyer to revisit the rate card associated with the development team. According to the vendor, the development team's experience and technical skills have increased since the project started. Which of the following documents should the buyer review FIRST?