PK0-005 Practice Test practice questions, page 2 of 25, with answer review and explanations.
Question 6
A project manager submitted a request to extend the project schedule, and the CCB just approved the request. Which of the following should the project manager do next? (Choose three.)
Update the risk register.
Assign severity to the change.
Update the request log.
Analyze the impact to the schedule.
Notify the stakeholders.
Update the schedule.
Analyze risk.
Implement the change.
Question 7
During a gate review meeting, the deliverable was rejected by the customer. Review the dashboard. Part 1: Drag and drop each task, placing them in the correct order based on the project change control process. Part 2: Select the proper document(s) to be updated.
Question 8
A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization’s reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Choose two.)
Train users on the proper use of the system.
Escalate the issue to the CCB.
Hold sessions to understand user challenges.
Track system usage and report user activity.
Log the issue in the project risk register.
Create a memorandum of acceptable use.
Question 9
Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?
Daily stand-up
Project momentum
Performance feedback
Meeting minutes
Question 10
Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?