Question 91
During an audit, a project manager finds out that a contractor exceeded the overtime hours allowed by the contract. Which of the following tools should the PM use to share the details with the management team?
Time-tracking log
Issue log
Statement of work
Risk register
Question 92
A segment of a project has ended. Before moving on to the next segment, the project manager wants to assess if the work produced in the previous segment meets a high enough standard and if adequate resources are available to continue the project. Which of the following should the project manager do?
Review the progress reports.
Perform a gap analysis.
Coordinate a phase-gate review.
Set up touch points with the team.
Question 93
Which of the following can be used to determine whether a sample product is within an acceptable range?
Scatter diagram
Velocity chart
Control chart
Fishbone diagram
Question 94
A PM is evaluating whether an IaaS contract needs to be extended. When reviewing the system usage report, the PM realizes that usage is at 20% capacity. Which of the following actions should the PM take?
Continue to monitor the system performance.
Resize the resource utilization to reflect current needs.
Reinforce adoption over time.
Raise an item in the issue log.
Question 95
A company is implementing a new radar system from July to September. The project manager knows these months are the peak hurricane season for this region. Which of the following should the project manager develop to mitigate the risk to the project?