Question 36
Which of the following process requires elicitation techniques? (Choose two.)
Develop portfolio performance management plan
Develop portfolio roadmap
Manage portfolio value
Manage strategic change
Question 37
Where can you find legal constraints which may influence the organizational strategy and objectives?
Organizational Process Assets
Portfolio Reports
Portfolio Strategic Plan
Enterprise Environmental Factors
Question 38
You’re ranking projects using a scoring model consisting of a series of evaluation criteria. The above figure shows the score measure and the weight for each criterion. Which project has the highest priority?
Project 1
Project 2
Project 3
Project 4
Question 39
A portfolio manager compares strategic objectives, prioritizes objectives, and performs strategic assessments against current enterprise portfolios. Which kind of tools and techniques is he using?
Strategy Alignment Analysis
Cost-Benefit Analysis
Portfolio Component Inventory
Prioritization Analysis
Question 40
Which of the following documents mentions how an organization uses planned resources within a portfolio?