Question 26

A senior executive complained that he didn’t receive an invitation for a project steering committee. What should you do to handle this complaint?

  1. Forward the invitation for the steering committee to the senior executive
  2. Interview the senior executive to understand communication requirements
  3. Consult your supervisor
  4. Record the complaint in a risk register

Question 27

Your company wants to digitalize their business due to COVID-19. You determine whether it is preferable to add, modify, or terminate some components to ensure the portfolio objectives remain aligned with the organizational strategy and goals. Which tools and techniques are you using?

  1. Portfolio Component Inventory
  2. Prioritization Analysis
  3. Scenario Analysis
  4. Strategic Alignment Analysis

Question 28

You want to find the migration actions for an issue. Which artifact should you check?

  1. Portfolio Reports
  2. Portfolio Management Plan
  3. Portfolio Risk Management Plan
  4. Portfolio Risk Register

Question 29

The above figure illustrates a pair-wise comparison of different portfolio components with one another. Which portfolio component has the least priority?

  1. Project A
  2. Project D
  3. Project E
  4. Project F

Question 30

You have found that one of the vendors had a low reputation, and you are worried that they would provide low-quality service for your portfolio. What should you do next?

  1. Disapprove the project using this vendor
  2. Record this in the risk register
  3. Update the risk management plan
  4. Communicate the risk to stakeholders